Posted: Sun 6th Nov 2016

Wrexham Roadworks Update: 25 Sets Scheduled This Week

Wrexham.com for people living in or visiting the Wrexham area
This article is old - Published: Sunday, Nov 6th, 2016

A busy week for roadworks in Wrexham this week – so as usual expect some delays and diversions in some parts of the County Borough. 

In total there are 25 sets of roadworks, closures or other works either ongoing or scheduled to take place across the Wrexham over the next seven days. Expect road closures and temporary traffic lights in some instances.

If you want to know what roads to avoid or how long certain roadworks have left, then have a nose at our Roadworks guide. If there’s any roadworks we have missed off, then please email [email protected] and we will try our best to chase them up.

________________________________________________________

B5070 Holyhead Road Junc Chapel Lane, Chirk Gas Main Replacement
3 way traffic lights
From 05/10/2016 to 17/11/2016 Duration Expected delay < 5 mins
For further info: Wales and West Utilities
________________________________________________________

Henblas Street, Wrexham Lay new cables
ROAD CLOSURE
From 06/11/2016 to 06/11/2016 Duration 1 day Expected delay N/A
For further info: SPEN – 0845 2722424
________________________________________________________

A525 Ruthin Road, Wrexham Tree Maintenance
Stop & Go
From 06/11/2016 to 06/11/2016 Duration 1 day Expected delay < 5 mins
For further info: WCBC 01978 298989
________________________________________________________

A525 Ruthin Road, Wrexham Cycle path/Footpath scheme
3 way traffic lights
From 31/10/2016 to 03/12/2016 Duration 5 weeks Expected delay at Peak times
For further info: WCBC 01978 298989
Be Aware: Between Croesnewydd Road and Homestead Lane
________________________________________________________

A5152 Chester Road jct. Smithy Lane, Wrexham BT Cabling/ Ducting
Mobile Road Works
From 07/11/2016 to 16/11/2016 Duration 10 days Expected delay at Peak times
For further info: BT – 03700 500792
Be Aware: Works moving along Chester Road – junctions Grove Rd/Penymaes Ave.
Also jct Price’s Lane/Rhosnesni Lane.
09:30 – 15:30 with no weekend works
________________________________________________________

Maesgwyn Lane, Bowling Bank, Wrexham New water main
ROAD CLOSURE
From 07/11/2016 to 09/11/2016 Duration 3 days Expected delay N/A
For further info: Gallagher TM Co.
________________________________________________________

Bryn Lane, Wrexham Ind. Estate New entrance to Biomass Plant
3 way traffic lights
From 31/10/2016 to 14/11/2016 Duration 2 weeks Expected delay < 5 mins
For further info: Blue Arrow T.M. Ltd 01928 751761
________________________________________________________

Garth Road, Garth Water Network Repairs
2 way traffic lights
From 03/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________

Poplar Road, Penycae Water Network Repairs
2 way traffic lights
From 03/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________

Summerhill Road, Little Mountain Water Network Repairs
2 way traffic lights
From 03/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________

A539 Station Road, Overton Repair Mains Leak
2 way traffic lights
From 04/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________

Daleside Avenue, Wrexham BT Cabling/ Ducting
2 way traffic lights
From 04/11/2016 to 06/11/2016 Duration 3 Days Expected delay
For further info: GCN Ltd 01745 331551
________________________________________________________

A528 Overton Road, Marchwiel Footway Repairs
2 way traffic lights
From 07/11/2016 to 07/11/2016 Duration 1 Day Expected delay
For further info: WCBC – 01978 298989
________________________________________________________

Wrexham Road, Marchwiel Gas Main Replacement
2 way traffic lights
From 07/11/2016 to 25/11/2016 Duration 3 Weeks Expected delay
For further info: Wales and West Utilities 01792 326214
________________________________________________________

Cefn Road, Wrexham BT Cabling/ Ducting
2 way traffic lights
From 07/11/2016 to 09/11/2016 Duration 3 Days Expected delay
For further info: BT – 03700 500792
________________________________________________________

B5425 Rhosddu Road Jct Greenfield, Rhosddu Water Network Repairs
3 way traffic lights
From 07/11/2016 to 07/11/2016 Duration 9.30am – 1pm Expected delay
For further info: DCWW/Morrisons – 01745 405722
________________________________________________________

Mold Road, Gwersyllt Cyclic Maintenance
Lane Closure’s
From 07/11/2016 to 07/11/2016 Duration 1 Day Expected delay
For further info: WCBC – 01978 298989
________________________________________________________

A541 Mold Road, from Wrexham to Gwersyllt Cyclic Maintenance
Lane Closure’s
From 08/11/2016 to 08/11/2016 Duration from 9.30 for 1 day Expected delay
For further info: WCBC – 01978 298989
________________________________________________________

Pickhill Lane, Cross Lanes Water Network Repairs
2 way traffic lights
From 08/11/2016 to 11/11/2016 Duration 3 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________

Whitchurch Road, Raggs Hill Overhead Cable Works
2 way traffic lights
From 09/11/2016 to 09/11/2016 Duration 9.30 – 3.30pm Expected delay
For further info: BT – 03700 500792
________________________________________________________

Llan y Pwll Link Road, Wrexham Cyclic Maintenance
Lane Closure’s
From 09/11/2016 to 09/11/2016 Duration 9.30 – 3.30pm Expected delay
For further info: WCBC – 01978 298989
________________________________________________________

Straight Mile, Bangor on Dee Cyclic Maintenance
3 way traffic lights
From 09/11/2016 to 10/11/2016 Duration 2 Days Expected delay
For further info: WCBC – 01978 298989
________________________________________________________

Bryn Estyn Road, Wrexham Electricity Network Repairs
2 way traffic lights
From 09/11/2016 to 23/11/2016 Duration 2 Weeks Expected delay
For further info: SPEN – 0845 2722424
________________________________________________________

Berse Road, Caego Overhead Cable Works
2 way traffic lights
From 10/11/2016 to 10/11/2016 Duration 1 Day Expected delay
For further info: BT – 03700 500792
________________________________________________________

B5425 Llay New Road, Llay Resurfacing Works
Convoy System
From 03/11/2016 to 25/11/2016 Duration 3 Weeks Expected delay at Peak times
For further info: WCBC – 01978 298989
________________________________________________________



Spotted something? Got a story? Email [email protected]



Have a look at...

Delays in enshrining human rights treaties into law raise concerns among experts

Over 616,000 patients waiting to start NHS treatment in Wales

Weather warning issued with storms forecast this weekend

£4m plans submitted to transform old library in wrexham into creative hub

Wrexham Waterworld shortlisted for two national fitness awards

Senedd rejects motion calling for winter fuel payment cuts u-turn

Wrexham woman reflects on lifelong connection to Nightingale House

Fresh plans to build new homes near Acrefair social club

Police “unable to provide evidence” of 20mph speed limit’s impact on road safety in North Wales

Public sector pay rises won’t lead to cuts to services in Wales, says Mark Drakeford

5G phone mast planned near Wrexham supermarket to boost local connectivity

New traffic restrictions to tackle city centre “Wacky Races” roads