Wrexham Roadworks Update: 25 Sets Scheduled This Week
A busy week for roadworks in Wrexham this week – so as usual expect some delays and diversions in some parts of the County Borough.
In total there are 25 sets of roadworks, closures or other works either ongoing or scheduled to take place across the Wrexham over the next seven days. Expect road closures and temporary traffic lights in some instances.
If you want to know what roads to avoid or how long certain roadworks have left, then have a nose at our Roadworks guide. If there’s any roadworks we have missed off, then please email [email protected] and we will try our best to chase them up.
________________________________________________________
B5070 Holyhead Road Junc Chapel Lane, Chirk Gas Main Replacement
3 way traffic lights
From 05/10/2016 to 17/11/2016 Duration Expected delay < 5 mins
For further info: Wales and West Utilities
________________________________________________________
Henblas Street, Wrexham Lay new cables
ROAD CLOSURE
From 06/11/2016 to 06/11/2016 Duration 1 day Expected delay N/A
For further info: SPEN – 0845 2722424
________________________________________________________
A525 Ruthin Road, Wrexham Tree Maintenance
Stop & Go
From 06/11/2016 to 06/11/2016 Duration 1 day Expected delay < 5 mins
For further info: WCBC 01978 298989
________________________________________________________
A525 Ruthin Road, Wrexham Cycle path/Footpath scheme
3 way traffic lights
From 31/10/2016 to 03/12/2016 Duration 5 weeks Expected delay at Peak times
For further info: WCBC 01978 298989
Be Aware: Between Croesnewydd Road and Homestead Lane
________________________________________________________
A5152 Chester Road jct. Smithy Lane, Wrexham BT Cabling/ Ducting
Mobile Road Works
From 07/11/2016 to 16/11/2016 Duration 10 days Expected delay at Peak times
For further info: BT – 03700 500792
Be Aware: Works moving along Chester Road – junctions Grove Rd/Penymaes Ave.
Also jct Price’s Lane/Rhosnesni Lane.
09:30 – 15:30 with no weekend works
________________________________________________________
Maesgwyn Lane, Bowling Bank, Wrexham New water main
ROAD CLOSURE
From 07/11/2016 to 09/11/2016 Duration 3 days Expected delay N/A
For further info: Gallagher TM Co.
________________________________________________________
Bryn Lane, Wrexham Ind. Estate New entrance to Biomass Plant
3 way traffic lights
From 31/10/2016 to 14/11/2016 Duration 2 weeks Expected delay < 5 mins
For further info: Blue Arrow T.M. Ltd 01928 751761
________________________________________________________
Garth Road, Garth Water Network Repairs
2 way traffic lights
From 03/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________
Poplar Road, Penycae Water Network Repairs
2 way traffic lights
From 03/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________
Summerhill Road, Little Mountain Water Network Repairs
2 way traffic lights
From 03/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________
A539 Station Road, Overton Repair Mains Leak
2 way traffic lights
From 04/11/2016 to 07/11/2016 Duration 5 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________
Daleside Avenue, Wrexham BT Cabling/ Ducting
2 way traffic lights
From 04/11/2016 to 06/11/2016 Duration 3 Days Expected delay
For further info: GCN Ltd 01745 331551
________________________________________________________
A528 Overton Road, Marchwiel Footway Repairs
2 way traffic lights
From 07/11/2016 to 07/11/2016 Duration 1 Day Expected delay
For further info: WCBC – 01978 298989
________________________________________________________
Wrexham Road, Marchwiel Gas Main Replacement
2 way traffic lights
From 07/11/2016 to 25/11/2016 Duration 3 Weeks Expected delay
For further info: Wales and West Utilities 01792 326214
________________________________________________________
Cefn Road, Wrexham BT Cabling/ Ducting
2 way traffic lights
From 07/11/2016 to 09/11/2016 Duration 3 Days Expected delay
For further info: BT – 03700 500792
________________________________________________________
B5425 Rhosddu Road Jct Greenfield, Rhosddu Water Network Repairs
3 way traffic lights
From 07/11/2016 to 07/11/2016 Duration 9.30am – 1pm Expected delay
For further info: DCWW/Morrisons – 01745 405722
________________________________________________________
Mold Road, Gwersyllt Cyclic Maintenance
Lane Closure’s
From 07/11/2016 to 07/11/2016 Duration 1 Day Expected delay
For further info: WCBC – 01978 298989
________________________________________________________
A541 Mold Road, from Wrexham to Gwersyllt Cyclic Maintenance
Lane Closure’s
From 08/11/2016 to 08/11/2016 Duration from 9.30 for 1 day Expected delay
For further info: WCBC – 01978 298989
________________________________________________________
Pickhill Lane, Cross Lanes Water Network Repairs
2 way traffic lights
From 08/11/2016 to 11/11/2016 Duration 3 Days Expected delay
For further info: Dee Valley Water 01978 846946
________________________________________________________
Whitchurch Road, Raggs Hill Overhead Cable Works
2 way traffic lights
From 09/11/2016 to 09/11/2016 Duration 9.30 – 3.30pm Expected delay
For further info: BT – 03700 500792
________________________________________________________
Llan y Pwll Link Road, Wrexham Cyclic Maintenance
Lane Closure’s
From 09/11/2016 to 09/11/2016 Duration 9.30 – 3.30pm Expected delay
For further info: WCBC – 01978 298989
________________________________________________________
Straight Mile, Bangor on Dee Cyclic Maintenance
3 way traffic lights
From 09/11/2016 to 10/11/2016 Duration 2 Days Expected delay
For further info: WCBC – 01978 298989
________________________________________________________
Bryn Estyn Road, Wrexham Electricity Network Repairs
2 way traffic lights
From 09/11/2016 to 23/11/2016 Duration 2 Weeks Expected delay
For further info: SPEN – 0845 2722424
________________________________________________________
Berse Road, Caego Overhead Cable Works
2 way traffic lights
From 10/11/2016 to 10/11/2016 Duration 1 Day Expected delay
For further info: BT – 03700 500792
________________________________________________________
B5425 Llay New Road, Llay Resurfacing Works
Convoy System
From 03/11/2016 to 25/11/2016 Duration 3 Weeks Expected delay at Peak times
For further info: WCBC – 01978 298989
________________________________________________________
Spotted something? Got a story? Email [email protected]